Noida Metro work India’s fastest
The upcoming Noida-Greater Noida Metro link is witnessing the fastest-ever pace of construction in India, published in a media report. In a record time of six months from the date of award of the contract, the first U-girder for the corridor was put in place across two piers at Greater Noida’s Delta station on Friday.
Delhi Metro Rail Corporation (DMRC) officials said this is the fastest ever girder launched from the date of award of the civil contract – June 2015 – in the country.
Touted to be ready for trial runs by December 2017 and commercial operations by March 2018, DMRC officials now hope they will be able to roll out the Metro service before the scheduled timeline.
“We are confident that in view of the fast pace of construction of this line, it should be possible to open this section for the public a few months before the schedule”, said Mangu Singh, MD of DMRC.
The report said the first girder for the Noida-Greater Noida Metro track took less than half an hour to lift into place by two hydraulic cranes. About 30 engineers and supervisors carried out a smooth operation. DMRC plans to put into place another two U-girders in place this month. They will be located at sectors 148 and 71.
-
Guest Column4 weeks agoRetail Trends to Watch Out for in 2026
-
News2 weeks agoFractoProp Receives SEBI Registration for Ridhama Real Estate Fund
-
News4 weeks agoMumbai Real Estate Hits 14-Year High with Over 13,000 Property Registrations in February 2026
-
News2 weeks agoRise of Airport-Linked Real Estate: Opportunities Emerging Around Jewar
-
News3 days agoHow Noida International Airport Will Impact Property Prices
-
News4 weeks agoSavills India Celebrates Women’s Day with Continued Focus on Trust, Flexibility and Career Growth
-
News3 weeks agoGreenlands Global Private Limited Appointed as Managing Partner for Big FM Realty’s ₹1,200 Crore Mixed-Use Development
-
News2 weeks agoIndia Maintains Competitive Edge as Asia-Pacific Office Fit-Out Hub, Reports Knight Frank